Bid Time: 2:00 PM
Bids Delivered To: bid@pogueconstruction.com
Pogue Construction on behalf of the Mesquite ISD will be receiving bids for the early release packages for Horn 9th Grade Center Additions and Renovations. Bids will be due in the offices of Pogue Construction on November 3, 2022 @ 2:00 PM. Bids are to be submitted to bid@pogueconstruction.com. The scope of work to be quoted in this release are Electrical Panels Furnished & Delivered, Structural Steel, Roofing and HVAC Units Furnished & Delivered. Plans and specifications are available via isqft or at the Pogue Website. Architectural drawings are provided for reference only. Award and approval of these bid packages by the MISD School Board is scheduled for December 12, 2022. Construction is scheduled to begin February 27, 2023 and be completed by July 11, 2024.
Virtual Pre-Bid Meeting: 10/27/22 @ 1:30 PM