Midlothian ISD Irvin Middle School

← BACK TO ALL BIDS
Bid Date: March 1, 2018
Owner: Midlothian ISD
Lead Estimator: Kevin Hollenbeck
Phase: Past Projects
Location:

Pogue Construction has been selected as Construction Manager at Risk for the NEW 95,655 SF Midlothian ISD Irvin Replacement Elementary School. Proposals shall be delivered to Pogue Construction via mail, 1512 Bray Central Dr. Suite 300, McKinney, TX 75069 or email, bid@pogueconstruction.com by 2:00PM. Proposals are for the furnishing of all labor, materials and equipment, and performing all work required for Irvin Replacement Elementary School for Midlothian ISD, and in compliance with the project manual and drawings, and other contract documents, as prepared by Huckabee.

Bid Time: 2:00PM

Pre-Bid Conference: @ 10:30AM, Wednesday, February 21, 2018 at the MISD Administration Building, 100 Walter Stephenson Rd., Midlothian TX 76069
RFI Deadline: February 20,2018 @ NOON
NTP for Construction: March 20, 2018
Substantial Completion: April 26, 2019